Sierra Madre Gold and Silver – Ramp Up To 720tpd Throughput At The La Guitarra Mining Complex, Exploration Strategy Across La Guitarra and Del Toro Properties
The KE ReportShow Notes
Alex Langer, President and CEO of Sierra Madre Gold And Silver (TSXV: SM) (OTCQX: SMDRF), joins us to review the ramp up in throughput in operations at the La Guitarra silver-gold mine complex in Mexico, which includes 3 producing mines: La Guitarra, Coloso, and Nazareno. We look ahead to the ongoing 2-phase plant expansion and upcoming increased 30,000 meters of drilling planned across the La Guitarra District slated to begin here in Q4. Additionally, we discussed the path forward at the recently acquired Del Toro mining complex, and the increased drill program there to 30,000+ meters of drilling across that property package starting next year.
Throughput at the Guitarra processing plant has significantly increased following Phase 1 expansion modifications to the existing crushing and milling circuits. Daily production has reached up to a steady 720 tonnes per day ("tpd"). This represents more than a 40% increase versus the previous nameplate capacity of 500 tpd.
Further modifications to increase capacity are scheduled to be made following the commissioning of the new 11x12 ball mill, which is now installed. Sierra Madre has also accelerated underground development, and started the groundwork for the permitted dry stack tailings facility expansion. This is a key component of the eventual Phase 2 plant expansion plan to increase throughput to 1,200 tpd to 1,500 tpd.
Development has been accelerated at all three of the mines within La Guitarra - Guitarra, Nazareno and Coloso - to provide feed to the expanded plant. Approximately 2.6 kilometers of development drives have been completed since June 2026. As haulage ramps are being driven both vertically and downward from the 180-access level, this ramp development is expected to allow for additional production areas to be developed. Since July 2026, over 800 meters of access and production drives have been completed.
For the balance of the discussion Alex outlined the aggressive 30,000+ meter exploration plan about to commence across the La Guitarra district land package. There will be a drilling focus on the East District, at past producing historic mining areas like Mina de Agua and El Rincon.
The company will also embark on a parallel 30,000+ meter program next summer across their Del Toro complex. In June 2026, Sierra Madre closed the acquisition of the Del Toro silver mine, adding a past-producing, fully permitted asset of 3 mines and a 3,000 tpd plant to its Mexico-focused silver and gold portfolio.
Click here to follow the latest news from Sierra Madre Gold & Silver
If you have any questions for Alex regarding Sierra Madre Gold and Silver, then please email them to us at either [email protected] or [email protected].
In full disclosure, Shad is a shareholder of Sierra Madre Gold and Silver at the time of this recording, and may choose to buy or sell shares at any time.
For more market commentary & interview summaries, subscribe to our Substack reports:
The KE Report: https://kereport.substack.com/ Shad’s resource market commentary: https://excelsiorprosperity.substack.com/
Investment disclaimer: This content is for informational and educational purposes only and does not constitute investment advice, an offer, or a solicitation to buy or sell any security. Investing in equities and commodities involves risk, including the possible loss of principal. Do your own research and consult a licensed financial advisor before making any investment decisions. Guests and hosts may own shares in companies mentioned.
More from The KE Report
Jason Jessup, CEO and Director of Magna Mining Inc. (TSX: NICU) (OTCQX: MGMNF) (FSE: 8YD), joins me to review the key takeaways from Pre-Feasibility Study (“PFS”) for the 100% owned Crean Hill Project, located in the South Range of the Sudbury Basin, northeastern Ontario. We go on to discuss the dual-track development of Levack and Crean Hill over the next couple years and the bigger picture vision of growth from the deep pipeline projects beyond that.
In this Company Update, Cory chats with Simon Dyakowski, President & CEO of Aztec Minerals Corp. (TSX-V: AZT | OTCQB: AZZTF). Aztec Minerals recently announced assay results from its Tombstone Project in Arizona, successfully extending gold-silver mineralization up to 190 meters west within the newly targeted North Extension. With more drill results coming, an upcoming maiden resource estimate, and a recently closed financing, Simon provides key technical and corporate insights into what is shaping up to be a pivotal quarter. Key discussion points include:
In this Company Update, I chat with Dr. Paula Muto, Founder and CEO of Apptly Health Technologies Corp. (CSE: APPT | OTCQB: APTHF). Dr. Muto discusses the platform’s ongoing expansion, major strategic partnerships, and how direct-pay access is reshaping specialist healthcare for patients, providers, and self-insured employers. Key discussion points include:
Welcome to this Daily Editorial edition of The KE Report. In this Daily Editorial, Cory and Shad chat with Joel Elconin, Co-Host of the PreMarket Prep Show and Founder of the Stock Trader Network, to break down a turbulent day across the broader markets. While headline tech names face steep selling pressure following major earnings updates, capital is staging an aggressive migration into classic defensive sectors, retail names, and fixed income.
John Miniotis, President and CEO of AbraSilver Resource Corp (TSX: ABRA) (OTCQX: ABBRF), joins me to review the best gold intercept drilled to date below the known mineralization at the Oculto deposit, in the ongoing Phase 6 drill program on the Company’s wholly owned Diablillos property in the mining-friendly provinces of Salta and Catamarca, Argentina. We also discuss the valuation mismatch in light of all the value-creation just in 2026, and the growth initiatives along the pathway to construction of the mine and future production in 2029.