Show Notes
Dan Fesenmeyer, Managing Partner at WindQuest Advisors, joins to discuss the repowering rush and the FAA permitting stall, rising O&M costs on larger turbines, tariff pass-throughs, and AI data center demand.
Sign up now for Uptime Tech News, our weekly newsletter on all things wind technology. This episode is sponsored by Weather Guard Lightning Tech. Learn more about Weather Guard's StrikeTape Wind Turbine LPS retrofit. Follow the show on YouTube, Linkedin and visit Weather Guard on the web. And subscribe to Rosemary's "Engineering with Rosie" YouTube channel here. Have a question we can answer on the show? Email us!
Welcome to Uptime Spotlight, shining light on wind energy's brightest innovators. This is the progress powering tomorrow
Allen Hall: Dan, welcome back to the podcast.
Dan Fesenmeyer: It's great to be here. Great to see you again.
Allen Hall: There is so much happening in your particular area. Your name pops up quite a bit within Weather Guard because, uh, we're dealing with a lot of operators and- A number of times we'll ask them, "Have you read your turbine supply agreement?"
"No." "Have you read your full service agreement?" "No." "Well, maybe you should do that." And then we say, "Have you talked to Dan? You should call Dan, 'cause he can help you understand what you have signed." Mm-hmm. "Oh, that's probably a good idea." So now that you're here, WindQuest Advisors, of course, obviously is your company.
Mm-hmm. And you're talking to a number of operators. The, the big hurdle at the minute, the nearest short-term hurdle, is repowering. There's just a lot of [00:01:00] repowering efforts going on- Mm-hmm ... trying to get turbines in, start a project. There's a July 4th deadline and an end of the year deadline. There's a couple deadlines after that.
What are you seeing right now from operators i- in terms of repowering? What's the effort happening?
Dan Fesenmeyer: Well, there was a ton of effort to start physical work. That window's obviously closing-
Allen Hall: Yes ...
Dan Fesenmeyer: very quickly, but it's still open. Uh, and then once you're past that window, my understanding is if you get your repower completed by the end of '27, you didn't really need to have started physical work.
But I think most folks, start physical work is kind of the insurance piece of it-
Allen Hall: Sure ...
Dan Fesenmeyer: if things take longer. Uh, another thing that's popped up is obviously FAA and other permitting.
Allen Hall: On the permitting side, from the federal's, uh, standpoint, is that stopped? Or, or are projects able to continue putting turbines in the ground, or what's the status?
Dan Fesenmeyer: My- From what I've seen, I think on the opening session here at [00:02:00] ACP, it was said, they said that there's, like, 130 projects that are-
Allen Hall: At least ...
Dan Fesenmeyer: caught. Yes. And I'm, I'm involved with some of them, and I have a fairly small shop, and there's just no FAA variances or permits or- They're not issuing- ... mitigation studies.
Everything seems to have stopped.
Allen Hall: So they're not even reviewing the documentation that's been submitted by the operators at all?
Dan Fesenmeyer: That's what it seems, yes. Yeah.
Allen Hall: Is that legal? Uh, uh, usually those federal requirements have a timeline which they're able to review those permits and get them approved or disapproved them.
You're s- Right ... I think what I'm hearing is, what you're saying is they're not even looking at them.
Dan Fesenmeyer: That's correct. That's what I've heard and seen.
Allen Hall: Okay.
Dan Fesenmeyer: Yeah. Yeah.
Allen Hall: So what is an operator to do then? How does this, how do they meet some of these deadlines if they can't get the permit?
Dan Fesenmeyer: Well, I mean, it stalled a lot of projects 'cause of the associated risk with it.
Although I've seen some, uh, you know, some repower folks think, "Well, you know, I'm just repair- repowering like for li
More from The Uptime Wind Energy Podcast
This week we’re revisiting our discussion with Andrew Davis of Tightline Composites and Brad Schmidt of Avient, who discuss a resin additive that eliminates peel ply on carbon planks.
Nordex Q3 orders jump 30% and Vestas lands about a gigawatt in Australia. Plus why turbine factories skip Australia, high project costs, and whether batteries can replace coal.
Allen covers the Trump administration’s bid to reopen Revolution Wind’s permit, a bipartisan Senate permitting deal, Nordex’s doubled third-quarter profit, and GE Vernova’s new wind chief.
Jeremy Heinks, founder and CEO of CICNDT, joins to discuss the inspector shortage, Level III oversight, blade samples, drone thermal limits, and IEC updates.
Vestas CEO Henrik Andersen says China barred Vestas from monitoring its own turbines. Plus Ørsted takes heat for Chinese monopiles, India’s blade design gap, and tents that beat weather delays.