Cheap power means nothing if the government turns against you. Giannis Andreou, CEO of Bitmern Mining, started hosting Bitcoin miners in the UAE on agricultural power below 6¢/kWh, was forced out when the government banned that power, moved to Ethiopia, and is now watching the same story repeat as the Ethiopian government takes over mining and large operators pack up and leave.
Giannis breaks down what went wrong in both countries, why it took 45 days to get his miners out of the UAE, how Ethiopia's uptime fell to 70% before things got worse, and why exporting miners from Ethiopia comes with a 35% tax. His conclusion: own the land and the infrastructure, or don't build on it at all.
We also cover his pivot to buying two farms in Texas (5.5 MW and 8 MW), why AI data centers pay 17 to 25¢/kWh while he found power at 3.9¢, why he stopped retail hosting, a 20 MW joint venture opportunity in Brazil, and how he borrowed against mined Bitcoin to pay for power at $25K and held it to $107K.
Nothing discussed is financial advice. Do your own diligence before making mining or hosting decisions.
Guest: Giannis Andreou, Founder & CEO of Bitmern Mining Bitmern Mining: https://www.bitmernmining.com Bitmern on YouTube: https://www.youtube.com/@bitmernmining Giannis on X: https://x.com/gandreou007 Giannis on Instagram: https://www.instagram.com/gianisandreou Giannis on LinkedIn: https://www.linkedin.com/in/giannisandreou/
Timestamps:
0:00 Intro 0:46 From crypto YouTuber to Bitcoin miner 2:23 Central banks and the case for mining 4:21 Greece, Cyprus and the banking crisis 6:39 Why the UAE in 2023 7:35 Agricultural power below 6¢/kWh 8:43 Renting farms vs building your own 9:29 How to choose a hosting partner 11:07 Leaving the UAE: 45 days to move miners 12:30 UAE loopholes and $600K per MW capex 13:38 Ethiopia: from great to complete disaster 15:02 The lesson: own the land and the farm 15:45 Sponsor: Altair Technology 16:16 Why 30 minutes from the airport is a red flag 17:40 The pivot: buying 5.5 MW and 8 MW in Texas 18:37 Bitcoin mining vs AI: 3.9¢ vs 25¢/kWh 21:12 Why he stopped retail hosting 22:56 Finland, Norway and the hidden costs abroad 23:44 Ethiopia's 35% export tax on miners 24:44 Manufacturer JVs and 20 MW in Brazil 25:51 Is Bitcoin mining becoming institutional only? 27:31 Why hashrate didn't drop at $60K 28:36 Will Bitcoin average above $120K? 30:31 Borrowing against BTC to pay for power 32:51 Communicating downtime to customers 34:18 Bribes, quotas and the 20% energy rule 35:24 Wrap-up
Sponsored by:
Altair Technology. ASIC hardware, replacement parts and mining infrastructure Code: HASHRATEUP https://altairtech.io/aff/125/
HashrateUp Hardware Deals: https://t.me/hashrateup Free 5-Day Bitcoin Mining Course: https://hashrateup.com/newsletter-sign-up/
#BitcoinMining #Ethiopia #UAE #BitmernMining #TexasMining #MiningHosting #HashrateUp
More from HashrateUp - A Bitcoin Mining Podcast
Curtailing your mine can cost you more than running it. Dan Lawrence, CEO and co-founder of OBM, started mining in a garage in Maryland in 2017 and built Foreman to stop driving an hour to reboot machines. Today Foreman turns Bitcoin miners on and off based on power prices, profitability and grid stress. Now Dan is building Vantage, a platform that reads the utility meter every 10 seconds and shows miners what their power bill really looks like.
HashrateUp Hydro Hosting is live: enterprise-grade, hydro-cooled hosting in Texas, now open to small miners starting at just one machine. 👉 Get started: https://hashrateup.com
Public Bitcoin miners shed about 75 EH/s in the first half of 2026, roughly $1.5 billion worth of mining hardware, as their power moves to AI. In this NEWS episode, Jesse breaks down who is leaving, where the hashrate is going and what it means for the miners who stay.
Texas is ending 4CP. The incentive that saved flexible miners roughly $50,000 per MW per year is likely in its final season, and ERCOT is moving toward 12CP by 2028. Haley Thomson, Director of Energy at Luxor, explains what that means for Bitcoin miners and who ends up paying for the grid.Haley breaks down how 4CP actually works, why firm loads are pushing for change, and how 18+ GW of new battery storage has compressed capacity prices across ERCOT. We also cover why Bitcoin mining is close to the perfect grid-balancing load, how batteries and miners compare as grid assets, and how Luxor performed what's likely the first 4CP curtailment of GPUs in ERCOT.We also walk through the Luxor Energy dashboard live, from tracking load against breakeven to iMiner underclocking, 4CP buffer settings and what it really costs to be online during a peak. At the time of recording, 4CP season 2026 was likely already over.This episode is not sponsored by Luxor. Nothing discussed is financial advice. Do your own diligence before making energy or mining decisions.Guest: Haley Thomson, Director of Energy at Luxor TechnologyLuxor Energy: https://luxor.tech/energyHaley on Hashrate Index: https://hashrateindex.com/blog/author/haley/Luxor: https://luxor.techTimestamps:0:00 Intro0:45 Can AI provide grid flexibility?1:31 The first GPU 4CP curtailment in ERCOT3:45 What 4CP is worth: ~$50K per MW per year6:02 How 4CP works and who pays for the grid8:54 Why Bitcoin mining is the perfect flexible load11:45 Adding 60 GW of renewables: the transmission bottleneck14:00 Why firm loads want 4CP gone16:43 How miners lower off-peak energy prices20:57 Renewables, congestion and transmission costs24:54 12CP explained: what changes for miners29:29 Curtailing at $0 power: the solar mismatch31:04 How 18 GW of batteries reshaped ERCOT36:22 Battery vs Bitcoin mine39:10 Capex: batteries vs hydro vs air-cooled mining41:49 Luxor Energy dashboard walkthrough43:54 iMiner: raising breakeven from $75 to $90/MWh45:28 4CP buffer settings and risk48:58 What missing a 4CP peak really costs51:54 The AI pivot and tier-zero data centers55:11 Where to find Haley and Luxor EnergySponsored by:Altair Technology. ASIC hardware, replacement parts and mining infrastructureCode: HASHRATEUPhttps://altairtech.io/aff/125/HashrateUp Hardware Deals: https://t.me/hashrateupFree 5-Day Bitcoin Mining Course: https://hashrateup.com/newsletter-sign-up/#BitcoinMining #ERCOT #4CP #LuxorEnergy #HashrateUp
Matteo Spinosa, founder and CEO of Doefin, built the first accessible prediction market for Bitcoin miners to hedge difficulty. Doefin lets miners and traders take a directional view on network hashrate — or lock in revenue certainty before difficulty spikes — using a Polymarket-style venue where price equals probability.