Catalyst with Shayle Kann

The gas turbine crunch

Catalyst with Shayle Kann

Show Notes

Demand for turbines is growing fast, but so are lead times — causing serious headaches for developers and even cancellations. In Texas, one of six cancelled projects cited “equipment procurement constraints” as the reasons for its withdrawal.

Lead times are stretching to four years and sometimes more. Costs are climbing. So what’s behind the bottleneck?

In this episode, Shayle talks to Anthony Brough, founder and CEO of Dora Partners, a consulting firm focused on the turbine market. Shayle and Anthony cover topics like:

Why previous boom-bust cycles in turbine manufacturing have left the industry skittish — and why Anthony says leaders are approaching this new peak with “guarded optimism”

The competing demands on the turbine supply chain, including from power, oil and gas, and aerospace industries

How lead times have ballooned to four years and, in some cases, even longer

Factors affecting the market beyond load growth, like renewables, storage, affordable gas, and coal retirements

How investment in tech innovation has raised turbine efficiency

How the industry is preparing for hydrogen — if hydrogen scales up

Resources:

Latitude Media: Engie’s pulled project highlights the worsening economics of gas

Latitude Media: High costs, delays prompt withdrawal of five more Texas gas plants

Power Magazine: Gas Power's Boom Sparks a Turbine Supply Crunch

Marketplace: Will we have enough natural gas turbines to power AI data centers?

CTVC: 🌎 Gas turbine gridlock #236

Credits: Hosted by Shayle Kann. Produced and edited by Daniel Woldorff. Original music and engineering by Sean Marquand. Stephen Lacey is our executive editor.

Catalyst is brought to you by EnergyHub. EnergyHub helps utilities build next-generation virtual power plants that unlock reliable flexibility at every level of the grid. See how EnergyHub helps unlock the power of flexibility at scale, and deliver more value through cross-DER dispatch with their leading Edge DERMS platform, by visiting energyhub.com.

Catalyst is brought to you by Bloom Energy. AI data centers can’t wait years for grid power—and with Bloom Energy’s fuel cells, they don’t have to. Bloom Energy delivers affordable, always-on, ultra-reliable onsite power, built for chipmakers, hyperscalers, and data center leaders looking to power their operations at AI speed. Learn more by visiting BloomEnergy.com.

Catalyst is supported by Third Way. Third Way’s new PACE study surveyed over 200 clean energy professionals to pinpoint the non-cost barriers delaying clean energy deployment today and offers practical solutions to help get projects over the finish line. Read Third Way's full report, and learn more about their PACE initiative, at www.thirdway.org/pace.

More from Catalyst with Shayle Kann

Oct 15, 2026

As data center-driven load growth continues to rise, hyperscalers are turning to natural gas – both in front of and behind the meter — to secure power. But whether the natural gas pipeline system has the bandwidth to support this surging demand remains far from certain.

Oct 8, 2026

Of all the concerns surrounding the AI boom, data center water usage tops the list. Opponents claim that massive hyperscaler facilities threaten local drinking supplies and drain aquifers. Proponents say data centers use a negligible amount of water, at least compared to agriculture or conventional power generation sources.

Oct 1, 2026

It’s been a wild few years for grid-scale batteries in Texas. At the start of the decade, the Lone Star State was home to roughly 200 megawatts of battery capacity. Today, that number has skyrocketed to seventeen gigawatts…with at least five more gigawatts expected to come online by the end of 2026.

Sep 28, 2026

This is a partner episode, brought to you by Bloom Energy.

Sep 24, 2026

Dual-use technologies and the rise of defense tech are having a moment. But how does the defense sector approach innovations in energy that may be necessary to optimize its fleets?

See all episodes →