Pennsylvania regulators propose interrupting new large loads that haven't brought their own capacity before anyone else during PJM grid events, while a $60 billion debt package forms behind Broadcom's compute for Anthropic. Plus Colossus's 90-day leases, a Microsoft-linked New Jersey site's year of unpermitted NOx, and Amazon's $1 billion community pledge.
In this episode: 1. Pennsylvania PUC votes 4 to 0 to curtail new large loads first — Energy News https://energynews.biz/pennsylvania-puc-large-load-curtailment-tentative-order/ 2. Broadcom’s Syndicate Starts Raising $60 Billion for Anthropic’s AI Compute Buildout | AI Industry Today — AI Industry Today Desk https://aiindustrytoday.com/news/broadcoms-syndicate-starts-raising-60-billion-for-anthropics-ai-compute-buildout/ 3. xAI turns surplus GPUs into a leasing business as it chases more capacity — Diego Almada Lopez https://cryptobriefing.com/xai-leases-compute-anthropic-google/ 4. NJ data center polluted for a year before regulators stepped in — Latitude Media https://www.latitudemedia.com/news/nj-data-center-polluted-for-a-year-before-regulators-stepped-in/ 5. Amazon’s $1B plan to combat data center backlash draws more backlash - Ars Technica — Ars Technica https://arstechnica.com/tech-policy/2026/10/amazons-1b-plan-to-combat-data-center-backlash-draws-more-backlash/
Follow and rate The Data Center Daily on Apple Podcasts or Spotify. Feedback? Email [email protected]
More from The Data Center Daily
Entergy Arkansas and Google amend their West Memphis power deal to resolve an accounting fight over ratepayer charges while adding a 440 MW solar PPA, 1.4 GWh of batteries and new transmission. Also: Musk's 10 GW compute claim for SpaceXAI, TCEQ pulling its permit portal offline, and $35 billion of Chinese orders for an Nvidia workstation GPU.
PJM filed a FERC study agreement to evaluate roughly 9.6 GW of new data center load and 10.2 GW of generation at SB Energy's Flagship site in Pike County, Ohio, outside its interconnection queue. Also: AEP, X-energy and Amazon eye 960 MW of Xe-100 reactors in Indiana, Texas's data center permit freeze draws scrutiny, and Memphis deadlocks on a moratorium.
NiSource signs a 20-year, 1,100 MW supply deal with Microsoft, funded by Microsoft, and NERC's computational-load standards clear their final ballot. Plus AEP's $4 billion fuel cell plant for Google in Wyoming and a 7.5 GW gas campus in a Utah water filing.
Oregon's governor has paused air and water permits for data centers until July 2027, and DOE issued a heat-driven emergency order for PJM. Plus FERC's split vote on Duke's large-load transmission rules and Microsoft's multi-gigawatt plan for its Maia inference chips.
Google lands two power paths. Indiana regulators approved AES Indiana's $1.3 billion solar, storage and wires plan for its 390 MW Monrovia campus, the first test of the state's 80% large-load cost law. Separately, Constellation will spend $4.3 billion uprating 11 PJM reactors by 890 MW.