Heinrich’s transmission tax credit proposal lands as California hardens data-center cost rules and AWS moves to buy Hong Kong capacity, underscoring the same constraint across AI infrastructure: power access, cost allocation, and ownership of scarce sites are becoming strategic battlegrounds.
In this episode: Top stories: 1. Exclusive: Heinrich proposes 30% credit for long-haul transmission — Latitude Media https://www.latitudemedia.com/news/exclusive-heinrich-proposes-30-credit-for-long-haul-transmission/ 2. California Governor Signs Data Center Legislation - Stoel Rives LLP — Stoel Rives LLP https://www.stoel.com/insights/publications/california-governor-signs-data-center-legislation-california-public-utilities-commission-will-address-implementation 3. Digital Realty scales back Kansas data center to 450,000 square feet - Kansas City Business Journal — Kansas City Business Journal https://www.bizjournals.com/kansascity/news/2026/09/23/digital-realty-data-center-project-jayhawk-evergy.html 4. Amazon to Buy Grand Ming Hong Kong Data Centres- Mingtiandi — Mingtiandi https://www.mingtiandi.com/real-estate/data-centres/amazon-buying-hong-kong-data-centres-from-grand-ming-for-up-to-312m/ 5. FERC has options for modernizing PJM’s governance | Utility Dive — Utility Dive https://www.utilitydive.com/news/ferc-options-modernizing-pjm-governance-peskoe/830905/
Follow and rate The Data Center Daily on Apple Podcasts or Spotify. Feedback? Email [email protected]
More from The Data Center Daily
Entergy Arkansas and Google amend their West Memphis power deal to resolve an accounting fight over ratepayer charges while adding a 440 MW solar PPA, 1.4 GWh of batteries and new transmission. Also: Musk's 10 GW compute claim for SpaceXAI, TCEQ pulling its permit portal offline, and $35 billion of Chinese orders for an Nvidia workstation GPU.
PJM filed a FERC study agreement to evaluate roughly 9.6 GW of new data center load and 10.2 GW of generation at SB Energy's Flagship site in Pike County, Ohio, outside its interconnection queue. Also: AEP, X-energy and Amazon eye 960 MW of Xe-100 reactors in Indiana, Texas's data center permit freeze draws scrutiny, and Memphis deadlocks on a moratorium.
NiSource signs a 20-year, 1,100 MW supply deal with Microsoft, funded by Microsoft, and NERC's computational-load standards clear their final ballot. Plus AEP's $4 billion fuel cell plant for Google in Wyoming and a 7.5 GW gas campus in a Utah water filing.
Oregon's governor has paused air and water permits for data centers until July 2027, and DOE issued a heat-driven emergency order for PJM. Plus FERC's split vote on Duke's large-load transmission rules and Microsoft's multi-gigawatt plan for its Maia inference chips.
Google lands two power paths. Indiana regulators approved AES Indiana's $1.3 billion solar, storage and wires plan for its 390 MW Monrovia campus, the first test of the state's 80% large-load cost law. Separately, Constellation will spend $4.3 billion uprating 11 PJM reactors by 890 MW.